In the rapid application development (RAD) model, which phase is similar to the final tasks in the SDLC implementation phase?

Prepare for the System Analyst Exam! Utilize practice tests, flashcards, and detailed explanations to boost your confidence and knowledge. Ace your exam with comprehensive study materials!

In the rapid application development (RAD) model, the cutover phase aligns closely with the final tasks of the implementation phase in the software development life cycle (SDLC). During the cutover phase, the focus shifts to transferring the completed application into a live environment. This includes finalizing deployment activities, converting data, training users, and ensuring that the system integrates smoothly with existing processes.

This phase emphasizes quick development and deployment, characteristic of RAD, where the goal is to minimize traditional implementation timelines while ensuring that the product is ready for end-users. By carefully managing this transition, the cutover phase ensures that users can access and utilize the application effectively, mirroring key activities in the SDLC implementation phase where the system is introduced into production and becomes operational.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy